CLIENT
WestConnex M4-M5 Link
PROJECT
Four Storey Site Construction Building
CONTRACT VALUE
$3.3 million
CONTRACT PERIOD
20 weeks
MBS were engaged to design and construct a 2,016m2 Four Storey Site Construction Building that included offices, locker rooms, shower rooms, training rooms, crib and amenities. The building was located over the decline tunnel that is to be used by the tunnelling team so close collaboration was needed during the design phase to work with the client on a suitable structure to clear span the 14m wide tunnel opening.
CRITICAL SUCCESS FACTORS
- Precise traffic management and installation planning was executed due to Sydney city site that had very minimal site access
- Designing fire engineering and structural solutions required for four storey construction
- Achieving delivery in full and on time for the WestConnex team