CLIENT
Schools Infrastructure NSW
PROJECT
Greystanes High School Gym & Drama Building
CONTRACT VALUE
$600,000
CONTRACT PERIOD
18 weeks
MBS were contracted to build a new Gym and Drama facility that was designed to the client’s brief, EFSG and all BAC requirements. The buildings required additional and reinforced floor joists and double layers of flooring to ensure the building was suitable for the additional live floor loads required for the gym and drama areas. The project was successfully completed safely and on time.
CRITICAL SUCCESS FACTORS
- Compliance with the EFSG
- Engineering the flooring for the gym and drama space to fit for purpose
- Working closely with the client to coordinate demolition of existing structure and preparation of the site